Analisis Penjadwalan Dengan Menggunakan Kurva S Pada Proyek Pembuatan Reactor Tank 30m3

  • Giyo Sekhan Abdillah Fakultas Teknik, Universitas Pembangunan Nasional �Veteran� Jawa Timur
  • Minto Waluyo Fakultas Teknik, Universitas Pembangunan Nasional �Veteran� Jawa Timur
Keywords: Projects, Construction, Project Management, Scheduling, S Curve Method

Abstract

Construction project activities can be defined as an activity that takes place within a limited period of time that has been determined with the allocation of certain resources and is intended to produce products whose quality criteria have been clearly outlined. In completing a construction job, scheduling is one of the things that is very important and needs to be paid attention to. PT. PDK received various projects, one of which was making a 30m^3 reactor tank. This tank work was carried out at the PT workshop. Putra Dharma Kencana. The S curve is a curve that describes the relationship between the accumulated value of development project implementation and project implementation. The weight on the S curve is the percentage of price for each job divided by the total price. If the total weight value is less than 100% then there is an error in the calculation which will affect the S curve. Work on the reactor tank was carried out according to the target, namely for 12 weeks. The disadvantage of the S curve method is the weight calculation. The weight used is the percentage of the price for each job with the total price.

Downloads

Download data is not yet available.

References

[1] N. Saputra, E. Handayani, and A. Dwiretnani, �Analisa Penjadwalan Proyek dengan Metode Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi,� Jurnal Talenta Sipil, vol. 4, no. 1, p. 44, Feb. 2021, doi: 10.33087/talentasipil.v4i1.48.
[2] D. M. R. Riesna, D. E. Pujianto, A. J. I. Efendi, B. A. Nugroho, and D. I. S. Saputra, �Identifikasi Platform dan Faktor Sukses dalam Manajemen Proyek Teknologi Informasi,� Jurnal Teknologi Riset Terapan, vol. 1, no. 1, pp. 1�9, Jan. 2023, doi: 10.35912/jatra.v1i1.1458.
[3] N. Maelissa, W. Gaspersz, S. Metekohy, and P. N. Ambon, �DAMPAK PANDEMI COVID-19 BAGI PELAKSANAAN PROYEK KONSTRUKSI DI KOTA AMBON,� JURNAL SIMETRIK, vol. 11, no. 1, [Online]. Available: https://ekonomi.bisnis.com/
[4] K. J. Santoso, K. Arianto Wijaya, H. P. Chandra, and S. Ratnawidjaja, �POTRET INDUSTRI KONSTRUKSI DI SURABAYA DALAM MASA PANDEMI COVID-19�.
[5] D. Darmawan and A. Ratnasari, �RANCANG BANGUN SISTEM INFORMASI MANAJEMEN PROYEK BERBASIS WEB PADA PT SEATECH INFOSYS,� Jurnal Sisfokom (Sistem Informasi dan Komputer), vol. 9, no. 3, pp. 365�372, Sep. 2020, doi: 10.32736/sisfokom.v9i3.931.
[6] M. P. Putri and B. Bobby, �Sistem Informasi Manajemen Proyek PT. Samudera Perkasa Konstruksi Berbasis Web,� MATRIK?: Jurnal Manajemen, Teknik Informatika dan Rekayasa Komputer, vol. 20, no. 1, pp. 85�96, Sep. 2020, doi: 10.30812/matrik.v20i1.716.
[7] P. DI Dinda Sulistia and I. Deliyarti Agustina, �PENJADWALAN PROYEK DENGAN KURVA-S PADA PERUMAHAN KOTA BEKASI,� Jurnal Al Ulum LPPM Universitas Al Washliyah Medan, vol. 11, no. 2, 2023.
[8] A. Arthono, B. Pratama, and A. Saputra, �Analisis Kinerja Proyek dengan Metode Earned Value: Studi Kasus Proyek Pembangunan Unit Sekolah Baru SMKN Kec. Serpong Kota Tangerang Selatan,� 2023, [Online]. Available: http://jurnal.polimdo.ac.id/
[9] K. Isnandar, M. Rahman Rambe, and N. R. Puspita, �Analisis Penjadwalan Proyek Gedung Puskesmas Padangmatinggi Kota Padangsidimpuan Menggunakan Metode CPM (Critical Path Method),� Jurnal Teknik Sipil, vol. 6, no. 1, pp. 19�30, 2023, [Online]. Available: https://jurnal.ugn.ac.id/index.php/statika
Published
2025-01-07
How to Cite
Abdillah, G. S., & Waluyo, M. (2025). Analisis Penjadwalan Dengan Menggunakan Kurva S Pada Proyek Pembuatan Reactor Tank 30m3. Jurnal Penelitian Dan Pengkajian Ilmiah Eksakta, 4(1), 8-13. https://doi.org/10.47233/jppie.v4i1.1772